In SAP APO, Production Planning/Detailed Scheduling (PP/DS) is used to generate procurement proposals to meet the production requirements. This component is also used for defining resource plan and order details. You can also plan for critical products to reduce the lead time and to improve time delivery performance.

 

PP/DS can be used to create executable plans and to achieve the following −

 

PP/DS is integrated with other SAP APO components. For example, with demand planning to create a demand plan and to move PIR to PP/DS to create procurement proposals.

 

Transaction and master data from the OLAP system is moved to APO and after order processing planning, results are moved to the APO system.

 

Integration of PP/DS with SAP APO applications

Let us now discuss the integration of PP/DS with SAP APO applications.

 

Integration with Demand Planning

Demand planning is used to meet the market demand for critical products after considering different factors and the result of demand planning is a demand plan. Demand plan is moved to PP/DS to raise procurement proposals for both external system and internal procurement process.

 

Using Demand Plan, demand planning is executed for customers and planned independent requirement results are transferred from DP to PP/DS to cover PIR by creating procurement proposals.

 

Following is the Process Flow −

 

Integration with SNP

Supply Network Planning (SNP) ensures that product quantities are available at the right time, a right place without overloading of resources in production and transportation process. SNP defines the quantities in which products should be procured, produced, or transported. PP/DS defines lot sizes of products to be procured, and sequences of planning order.

 

Both the methods are integrated and planning is performed for different task distribution.

 

Supply Network Planning and PP/DS Planning Tasks

SNP and PP/DS are defined for different phases - SNP planning is used for medium-term objectives and short-term planning is for PP/DS. The horizon for SNP planning and PP/DS planning are the same and the planning area doesn't overlap.

 

When the same planning version is used for SNP and PP/DS, it is also possible to convert SNP orders into PP/DS orders.

 

PP/DS Alert Monitoring

You can monitor alerts raised in PP/DS planning using the Alert monitor. You need to define an alert profile relevant for your planning. Different alert types are created in PP/DS.

 

Alerts Related to Relationship between Orders or Operations